Spring 2012 Construction Update – Cornell Edition

9 05 2012

The new Food Sciences Building has completed a substantial amount of exterior work, although the glass facade has yet to be installed. The $105 million renovation is to be completely done in early 2014, with the new Dairy Bar sometime earlier than that.

Site prep is underway at Gates Hall (the new Computer Science building). The $60 million, 103,000 sq ft building is targeting a December 2013 completion date.

It’ll be a happy day when these plain beige boxes are removed. Unfortunately, the $51 million renovation of Warren Hall that necessitated their construction will not be complete until early 2015 (with the Dyson School portion complete by mid-2013 – and it annoys me to refer to the AEM Department as the Dyson School, as if the perceived pedigree was needed to remove themselves from the stigma of CALS).

Not the most telling image, but Rice and Fernow Halls are currently in the middle of their renovations.

This Bradfield-based photo of Fernow shows the partially-subterranean classroom being built on the east side of the building.





Spring 2012 Construction Update

2 05 2012

I’m disappointed, and I’m not disappointed. I can’t be at Slope Day itself because of a morning meeting (and to seal my fate that day, I’m having new tires put on my car). On the bright side, I did get a chance last weekend to go to a Cornell alumni reception for my major, and the traffic, one could assume, was a lot better than it would be with thousands of young alumni driving back to the area. I took the downtime between alumni events as an opportunity to do some construction photo updating.

As nice as it would’ve been to report on some downtown construction, all the sites approved or of buildings “underway” appeared to be dormant from the outside – if they’ve started anything, it might be interior demolition, but there wasn’t any demolition equipment at Seneca Way or Breckinridge Place (which, as I have now discovered, is scheduled for May 15th); the latter had a tarp poster, shown above, but that was about it. As kinda expected, significant work has yet to start at the Holiday Inn, Hotel Ithaca and Cayuga Green II.

That being said, it’s not like there was no progress at all in the area. The Argos Inn is nearing completion of its renovation.

Comparably, construction in Collegetown has been rapid. Here, 309 Eddy is undergoing facade installation, and looks on track for an August completion date.

The progress at Collegetown Terrace has been nothing short of astounding. The following photos try to convey a sense of the size and scope of the construction, but I feel they fail to do so. By Ithaca standards, this project is enormous.

Definitely not a fan of the giant concrete pedestal.Here’s to hoping it gets landscaped into obscurity.

The Ithaca College Boathouse nears completion on Inlet Island.

So, this one I only came around by chance, as I was going out with old friends for dinner. Apart from them thinking I’m nuts for taking photo of a building under construction, I’d say this was a pleasant surprise. The building is Magnolia House, a 14-person women’s homeless shelter.

The Coal Yard Apartments Phase II is virtually complete. The 4-story building holds 25 apartments.

The Vine Street Cottages development continues, with the model unit currently the only building under construction. The project includes 19 houses and 10 townhomes.

Seeing as my computer is lagging substantially with the uploading of all these photos, I think I’ll cut myself some slack and upload the Cornell project photos in a later entry next week.





A Snowy Ithaca Update

30 12 2011

It’s a running joke that Ithaca is “centrally isolated”. Luckily for me, however, I grew up not too far north of Syracuse, so visiting my family for the holidays can also have “pay a visit to Ithaca to update my photo collection” somewhere on the itinerary.

Unfortunately, although I had the date planned well in-advance (I even wrote a list of places to visit so I wouldn’t miss any of my intended targets), it also happened to be one of the coldest and snowiest days yet of the upstate winter. The lake effect had set itself up in a large and fairly strong band south of Syracuse, enveloping a wide swath of land from about Ithaca up through Lafayette. With the passage of a cold front the night before, a brisk northwest wind kicked up, turning a snow day into a windy and snowy day, with near-whiteouts on the interstate.  Combine that with puddles from the heavy rain of the previous evening freezing over, and the driving was a bit of a harrowing experience. At least the old days of practicing controlled skids in a parking lot came in handy. Anyways, the weather slacked off after lunch and I was able to get some photos.

The BJ’s in Lansing (just north of the mall) is near completion. I did not notice any senior homes being built when I visited.

One of the housing projects nearby, Ivar Jonson’s Heights of Lansing. 6 more units of the 80 unit project are under construction in the background. I took photos of some of the Lansing suburban sprawl, but I figured no one would know the difference between a cul-de-sac of McMansions here vs. any other city. I’ll save the photo for another entry that could better use it.

Not much happening with the Ithaca Gun site. The site is cleared, but no construction has taken place. According to an article in the Ithaca Journal, the project is supposed to finish clean-up this year, and the developer plans to finish clean before starting any redevelopment. So probably no construction until 2013.

The site of the Breckenridge Place project. The Women’s Community Building’s days are numbered. According to a very recent Ithaca Times piece, demolition will occur starting in March.

Rendering Courtesy fo Hart Hotels

 

The Holiday Inn has begun the initial phases of proposal with the planning board. The plan calls for the low-rise portion, shown here, to be demolished, with a new conference area and a few more rooms attached to the mid-rise tower of 10 floors. The new hotel would be built at this street corner. I don’t have many faults with the design, except that the east wall looks cheap. Like 1960′s pre-fabricated cheap.

The Cayuga Green Condos site awaits construction. The project is currently unfunded (and therefore stalled), but with a reorganization and a ground floor tenant secured, the developers hope to secure funds and start construction by next summer.

It seems I’ll have a plentiful supply of “before” images. This is the Hotel Ithaca site. I’m willing to venture this project is much like the Cayuga Condos – tenant secured (Gemstone Hotels), but no funding yet in place as a result of the tight loan market for new projects. Hopefully, we’ll hear positive news in 2012.

Hm. I’m sure things will be much more interesting one year from now. Here’s the Seneca Way Apartments site. The renovation of the Argos Inn (turning a dilapidated house into a LEED-certified boutique hotel) continues in the background. The Seneca Way project will begin demolition of the old Challenge Industries building this spring, and be built on a (slow if steady) 18-24 month time frame.

Moving towards Collegetown, it was hard to fully capture the sheer size and scale of the Collegetown Terrace. Simply put, it’s massive. The house in the background to the left is the Williams House; the project extends further up the street beyond that. In contrast to Seneca Way, the time frame here is brisk – phase one, consisting of 12 of the 16 new buildings, is expected to be completed by August 2012. The other two phases are expected to be completed in 2013 through early 2014.

I did some mental math – the rental market will see Novarr’s 600 beds come online in the next couple of years, which might be around 5% of the total market. That’s quite an impact, most likely to be felt by the student-oriented apartment complexes furthest from campus.

The apartment building under construction at 309 Eddy. Look for a completion date around late summer 2012.

The site of the “Collegetown Crossings” project, formally known as 307 College Avenue. The project is back on the agenda as a sketch proposal, but I’m yet uncertain as to whether it keeps the form of a 6-story 60-unit building with a distinct lack of parking, or if the proposal has been modified.

EDIT 1/23/12: The above rendering (from the Sun, courtesy of the City of Ithaca) is the latest design of the project. The project, if granted approval, will be home to a Greenstar Co-Op Grocery branch. The building would be complete by 2014.

Phase II of the Coal Yard Apartments project off Maple Avenue. The 4-story, 25-unit project looks to be heading towards a spring 2012 completion date.

The site for the Vine Street Cottages project has been cleared. Construction of the model house should be complete by the spring. The 29-unit project (19 homes and 10  townhouses) effectively redevelops the eastern edge of the city (Belle Sherman).





News Tidbits 10/26/2011: I Can Barely Keep Up With All These Proposals

26 10 2011

When I started writing about construction projects, it seemed like they were relatively unreported by different news sources. Now it seems like I can’t avoid seeing an Ithaca Journal or Cornell Sun article detailing some construction project. I dunno if that’s because someone decided that construction is suddenly more noteworthy or if I’m just relatively more observant on these sort of things now that I live outside the area, and information is harder to retrieve. Lately, another reason might be that there’s been a ton of new projects coming down the pipeline.

In the latest Ithaca Times, it has been noted that Fairfield Inn project down in big box land, and the Seneca Way project, have both met their final approvals, which means sites can be cleared and construction can start hopefully in the near future. While that should be no problem for the hotel, the funding concerns with Seneca Way may cause some delays with that project, and it will be a waiting game to see when site prep begins and construction starts. Personally, I’m hoping to avoid a repeat of Ithaca Gun.

Image Courtesy of Cornell Daily Sun

As for new projects, a new sketch plan was proposed, informally referred to as the “Johnson’s Boatyard Housing Project”. The project is sited for Willow Avenue, which lies to the northwest of Fall Creek, on a parcel of land jutting out past Route 13 and across the inlet from Cass Park (so, right next to the city golf course). Apart from the boatyard, there are several light industrial and commercial properties, as well as some undeveloped space. Since the project is planned to be adjacent to Willow Avenue, I suspect it is within the already developed area.

Map Courtesy of Google Maps

The sketch proposal suggests three phases of development.  The first phase, to start next year, will build about 20 townhouses. The second and third phases will be multistory (2-4 floor) mixed use buildings (retail on bottom, apartments on top) built near or along Willow Avenue. Market conditions will decide the final scale and timeline for those phases.

Last but not least, and this falls more into the rumor mill, but Tompkins County is planning a Center of Government building in downtown to place all of its administrative services under one roof. The possibilities range from a new building on the site of the now-vacant old county library, or renovating and adding on more floors to adding 2 or three floors to the Board of Elections Building on Buffalo Street. The final decision will be made within the next several months.

So, quite a bit of news in the past month. The approval of the Breckinridge Project (52 apts, 6 floors), the approval of the Seneca Way Project (32 units + retail, 5 floors), the approval of the Vine Street Cottages project (29 units), the Holiday Inn expansion (9 floors), the approval of the Fairfield Inn project (4 floors), the announcement of the new Humanities Building (66,500 sq ft) and new information on Gates Hall (101,000 sq ft), the announcement of the Johnson Boatyard Project (20+ units)…just a lot of stuff lately. Which certainly isn’t a bad thing.





Homecoming Construction Update

19 09 2011

I came. I saw. I took photos. Note that all the photos can be enlarged by clicking on the image.

Milstein Hall – The building so nice I visited it twice (and by nice, I mean it’s “nice”, but not “great”, and hard to believe it cost $55 million). During the second visit on Saturday evening, a group of about ten skateboarders converged on the white humps and concrete curves. I’m going to guess it will only be a matter of time before that gets banned if it hasn’t been already.

The Human Ecology Building. The woman at the info desk offered up a “scavenger hunt” assignment, but I was short on time.

The Food Science Building (Stocking Hall Addition/Reconstruction). From my favorite Bradfield perch.


Prefabs on the Ag Quad. Sad face.

The Johnson Museum Addition

The Physical Sciences Building

309 Eddy Street. When they say “opening soon”, they mean next summer. I also have a photo of the Collegetown Terrace site from a distance, but I could see was a fenced-off area that was largely cleared out.





News Tidbits 8/22/11: Kappa Delta’s Swanky Renovation

22 08 2011

It would be nice to live in Ithaca, but since I don’t, I increasingly find about construction projects from word-of-mouth rather than investigating on my own. In correspondence with “BB” from the Milstein Hall entry, he briefly mentioned that he’d take some photos of KD’s renovation project.

It piqued my curiosity because that was the first time I had ever heard about it. My first thought was that it may not have been an immense piece of work because I hadn’t seen anything in the planning board minutes from the city. But, I decided to quickly check online to see if there was anything special about this construction project.

I barely recognized the house.

Here’s the before photo, from my own archives (dated July 16, 2008).

Here’s an after image from a construction blog on their website:

It’s a pitifully small photo, but I’ll rectify that when I take a photo at Homecoming. Note that the west wall (right side) visible in the before image is now the front entrance.

The most substantial change is the construction of a generous wrap-around porch from Sisson Place onto Triphammer Road. The construction itself isn’t expanding the structure much, about 800 sq. ft on the first floor (based off what my strained eyes can pull from the elevations image at top). But the exterior reclad with an emphasis on a traditional appearance does wonders for what was arguably one of the more rundown-looking sorority houses on campus, creating a more graceful, less bunker-like presence. According to the webpage, the renovation cost is around $400,000.

Regarding the comment on the webpage about Triphammer Road being the original entrance location, I don’t have any verification of that, but it is quite likely. KD moved to its current location around 1923 and underwent several renovations/expansions in the years since.

In terms of exterior alteration, this is probably one of the most substantial changes since Sigma Pi built a new house in the mid-1990s. I must admit that the final result looks impressive.





Exploring Milstein Hall

16 08 2011

So, fortunately for me, I’m not the only person out there who has an interest in Cornell construction projects. By good fortune, I happened to receive a series of emails from a newly minted Cornell graduate, “BB”, who took the time and opportunity to explore the nearly complete Milstein Hall and pass along some photos to this blog. For that I am thankful, as my trips to Ithaca have become fewer and further between. While I am glad for the photos, I’m still going to push the token disclaimers that I do not encourage or condone the exploration of unfinished buildings, due to a safety risk and legal concerns with trespassing. Also, while he is kind enough to share the photos here, they are his property, with all associated rights and privileges. I would encourage those that want to use his photos to contact him directly.

For those who wish they could answer nature’s call while on a spaceship…

They’re not even stalls. They’re more like bathroom pods.

I’m looking at this photo, and immediately, “The Imperial March” pops into my head.





An Exercise in Mapping, Part II

15 05 2011

Under Construction: The once-vacant Plantations Building on Ithaca Commons is being renovated into 8 apartments, a small amount of office space, and a large restaurant on the first floor of the 5-story building. The project is funded partially by community grant money and will be complete in about a month.

Approved: The 6-story, 52-unit apartment building proposed by INHS (1), the 7-story, 45-unit Cayuga Place condos (2), and the 10-story, 140-room Hotel Ithaca (3) are attempting to find financing in what is still a tight market for construction loans. The INHS building is dependent on state grant money that was not granted last year, and they are hoping to obtain financing in the next round of grants. The Cayuga Place condos has been looking for more unit sales and securing bank financing for almost four years at this point, and it might be time to move that to a stale proposal.

Proposed: The 6-story Challenge Industries redevelopment proposal, which has some office space and 32 units of housing. The project is currently trying to win over the neighbors and councils for zoning variances and approval down the line.

Stale/Dead: McGraw House, a senior living facility, was looking into a 25-50 unit expansion, and held several meetings to discuss proposals on the table, but this has all been tabled until a future time.

Examining the Ithaca College Area:

Note that I don’t use Bing Maps because I like them more, but because they are more up-to-date. For example, IC’s virtually complete Athletics Center is clearly visible on this aerial image.

Under Construction are Ithaca’s College’s Circle Apartments expansion (in the site prep stage; four current buildings (132 units) will be demo’d and nine more (280 units) will be added to the complex) and a 22-unit addition of senior housing (patio homes) to Longview.

Approved are the College Crossings retail center and INHS’s Holly Creek townhomes (11 units in first phase, I think 22 total). Off the map to the south and southwest are a couple of housing developments, Southwoods and Cleveland Estates, which are being developed lot-by-lot.

The proposed facility is the long-term expansion plans for the South Hill Business Campus, which would add 197,000 sq ft in three new buildings 3-4 stories in height. The campus currently has about 288,000 sq ft, of which about 84% is leased.

The stale proposal is an apartment building off of Bella Vista Drive that has been trying to market its units for the better part of five years. I am doubtful it will ever launch construction at this point.





An Exercise in Mapping

24 04 2011

So, I figured that since I write about Cornell, IC and Ithaca-area construction projects as much as I do, it might be nice to include some form of a map. Depending on time and motivation, I might get around to putting ones together for South Hill and Downtown.

So, Cornell Campus, used here primarily as a test bed (click the image to expand its size).

Under Construction:

1 – Milstein Hall 2- Johnson Art Museum addition 3- Human Ecology Building 4- Stocking Hall Addition

Approved:

1- Wilson Lab / Synchotron Expansion (CU ERL Project)

Proposed:

1- Gates Hall

Stale Proposals (i.e. been around a while, little notable progress in the past several months-plus)

1- Goldwin Smith Hall Addition 2- Gannett Health Center Addition 3- Holley Center (Soil Lab) Expansion (most likely dead, given federal budget cuts).

Heading south into Collegetown -

Under Construction

1- Coal Yard Apartments Phase II – A 4-story, 25-unit building off of Maple Avenue.

Approved:

1 – 309 Eddy Street (5 stories, 41 units) 2- Vine Street Cottages (19 house, 10 townhomes) 3- Collegetown Terrace (several buildings, 2-6 stories, 589 units)

Proposed:

1- 307 College Avenue (5 stories, 60 units), Snaith House addition (12 bedrooms)

Mall, Airport and Vicinity -

Under Construction:

1- BJ’s wholesale Club (82,000 sq ft) and 12 senior living units 2- Heights of Lansing (~17/80 units complete).

Approved:

1- Millcroft Housing Development (~19 lots in phase II).

Proposed:

1- Lansing Reserve Project (65 units) 2-  NRP Group Project (80 units)

Stale Proposal

1- Behind the mall, a mix of additional shops and 40 apartments, in a lifestyle-center setup, were proposed about three years ago. The recession may have killed the project; at the very least, it’s been shelved.

***

This isn’t to say there aren’t plenty of other projects in the area, I just wanted to experiment with presenting local projects in a different, more visual format.





Springtime Construction Update

12 04 2011

Long story short, for the first time since about New Year’s, I was able to visit Ithaca this past weekend. Went for a national initiation for the fraternal alma mater and stayed for the day.

Milstein Hall continues towards its late 2011 completion date.

The new Human Ecology Building nears completion.

The Brian Nevin Welcome Center for the Cornell Plantations is open and ready to receive visitors.

Demolition work continues on Stocking Hall’s “new wing”, to make way for the new Food Sciences building.

Concrete pouring is well underway for the Johnson Museum addition.

The site of Gates Hall, looking southeast.

Oh Cornell. Even if you drove me nuts while I was in Ithaca, I do miss you a little bit. Partly because I have to look at this everyday:

Good thing my office is windowless.








Follow

Get every new post delivered to your Inbox.