Upson Hall Construction Update, 9/2016

2 10 2016

Work on the upper levels is progressing. Slowly but steadily, mineral wool is being laid and aluminum clips are being installed for the terra cotta panels. It looks like the most progress has been made on the east facade. The windows in the bump-outs have received aluminum trim. Although the project update page hasn’t had a fresh post since early August, the upper floors (3-5) should be occupied by this point and many of the utilities systems have been overhauled. Most of the interior work is now focused on the lower levels (Basement, and Floors 1 and 2). The Pike Company of Rochester will continue the interior renovations during the academic year, but as long as all goes to plan, the building should be wrapped up by August (landscaping is another matter).

20160918_135255 20160918_135339 20160918_135401 20160918_135507 20160918_135535 20160918_135628 20160918_135742 20160918_135846


Actions

Information

Leave a comment